SKAWINA II work progress

SKAWINA 2 work progress

Skawina Ring Road Stage 2 - from Energetyków street to national road No. 44 together with construction of a bridge, construction of crossroads along DK44 and necessary infrastructure in the town of Skawina


The contract is financed from the national budget by the General Directorate for National Roads and Motorways [GDDKiA]. The Voivodeship Roads Authority [Zarząd Dróg Wojewódzkich] in Cracow is the investor, based on the Agreement of 29 July 2016 concluded between the Małopolska Voivodeship and Treasury - the General Directorate for National Roads and Motorways [GDDKiA]. Work progress as in November 2018:

 

skawina 2 etap budowy x 4

 

BRIDGE WORKS:
- excavation for the supports of the bridge - 100%;
- backfilling of excavations - 75%;
- construction of retaining walls 100%;
- execution of piles drilled in a draw-down pipe, fi 1000 to fi 1800 -100%;
- concrete reinforcement with A-IIIN grade steel - 05%;
- concreting of the foundation supports - 100%;
- concreting of 90% object supports;
- 100% leveling concrete;
- concrete of the 95% load-bearing structure;
- manufacture of a 100% steel structure;
- assembly of a 100% steel structure;
- anticorrosive protection of the 40% steel structure;
- installation of grooves 57%;
- installation of 44% dehydrating filters;
- bituminous insulation thin, 3-fold covering of concrete surfaces - 91%;
- assembly of 80% cup bearings;
- insulation made of 16% weldable roofing paper;
- protection of expansion joints between the bridge A and the retaining walls 100%.


Please see the work progress - Gallery